Deadly Hwy. 101 intersection was supposed to be fixed years ago. What happened?


Recommended Posts

  • Diamond Member

This is the hidden content, please

Deadly Hwy. 101 intersection was supposed to be fixed years ago. What happened?

A notoriously deadly Highway 101 crossing in northern San Luis Obispo County claimed another life this week as plans to fix the intersection are years delayed.

On Wednesday,

This is the hidden content, please
when she tried to cross the highway at Wellsona Road and drove into the path of an oncoming big rig.

The ****** was the latest in a history of fatal crashes at the site near the San Paso Truck Stop.

The intersection, which allows vehicles to cross Highway 101 unprotected, has a traffic collision rate higher than the

This is the hidden content, please
. Six people were ******* in crashes there between 2012 and 2016.

In the most recent 5-year *******, the intersection has experienced 16 collisions, according to Caltrans spokesman Jim Shivers. Of these, 14 were multi-vehicle collisions and three were fatal collisions, he said.

Map TemplateDeadly Intersection at Wellsona Road and Highway 101

The notoriously deadly intersection of Wellsona Road and Highway 101 near Paso Robles.

Map created with the assistance of ChatGPT.

Caltrans first announced plans to build an underpass at the site in 2017.

Construction was supposed to start two years ago, but aside from a few flashing warning beacons added as an interim measure to alert travelers to the potential for cross-traffic, work has yet to begin.

What’s happening?

The Tribune looked into the project’s delays as part of its Reality Check series.

What is planned at Wellsona Road?

After the county Board of Supervisors

This is the hidden content, please
, Shivers predicted at the time that construction would likely begin in winter 2022.

But only now is the

This is the hidden content, please
finally ready to get underway, Shivers told The Tribune.

Plans call for building an 112-foot undercrossing below Highway 101 just south of the existing intersection, eliminating the need for motorists to make left turns or drive straight across traffic on Highway 101.

data:image/gif;base64,R0lGODlhAQABAIAAAAAAAP///ywAAAAAAQABAAACAUwAOw==

A Caltrans project to install an underpass at the intersection of Highway 101 and Wellsona Road between Paso Robles and San Miguel is slated to begin construction in 2024.

This would prevent future broadside and left-turn merge-related collisions at the intersection, Shivers said.

If all goes according to the latest schedule, construction will begin by January 2025, he said.

Full closure of either Highway 101 or Wellsona Road is not anticipated for the project, he said.

“This will benefit a lot of people when completed,” Shivers said. “It will be a dramatic improvement to public safety.”

data:image/gif;base64,R0lGODlhAQABAIAAAAAAAP///ywAAAAAAQABAAACAUwAOw==data:image/gif;base64,R0lGODlhAQABAIAAAAAAAP///ywAAAAAAQABAAACAUwAOw==

One person ***** when a semi-truck and an SUV collided at the deadly Wellsona Road intersection on Highway 101 near Paso Robles on Wednesday, Aug. 28, 2024.

Why has it taken so long?

Caltrans hoped to have the undercrossing built by now, but Shivers said the delays are mostly routine.

“Project design and development takes time,” he said.

He said the largest obstacle has been securing land-use permits — known as right-of-way easements — from property owners in the area, causing them to push off the start date of construction.

“In this particular situation, we had right-of-way issues ahead of us to solve before we could move into construction,” Shivers said.

This is the hidden content, please

For the last few years, Shivers said, Caltrans has been in conversation with the neighboring property owners about aspects of the project.

At this point, they have acquired three of the parcels of land needed and have an agreement to move forward with construction on the fourth parcel located at the San Paso Truck Stop while the contracts to acquire it are still being finalized, Shivers said.

With all the appropriate right-of-way certifications in place, the project can finally break ground.

The now-$14-million project is entirely funded by the

This is the hidden content, please
, which specifically helps fund public safety projects, Shivers said.

The next step is for Caltrans to open a bid for a contractor, which Shivers expects to happen on Sept. 19.

Construction on the underpass would start by the new year and aim to be completed by early 2026, he said.

Until then, he advised drivers to be on high alert when driving through the area.

“We are eager to see this project to completion,” Shivers said. “We want this project as much as the public. We are looking forward to getting this one done.”

data:image/gif;base64,R0lGODlhAQABAIAAAAAAAP///ywAAAAAAQABAAACAUwAOw==data:image/gif;base64,R0lGODlhAQABAIAAAAAAAP///ywAAAAAAQABAAACAUwAOw==

The intersection of Wellsona Road and Highway 101 has been the site of several deadly collisions in recent years.



This is the hidden content, please

#Deadly #Hwy #intersection #supposed #fixed #years #happened

This is the hidden content, please

This is the hidden content, please

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Vote for the server

    To vote for this server you must login.

    Jim Carrey Flirting GIF

  • Recently Browsing   0 members

    • No registered users viewing this page.

Important Information

Privacy Notice: We utilize cookies to optimize your browsing experience and analyze website traffic. By consenting, you acknowledge and agree to our Cookie Policy, ensuring your privacy preferences are respected.